#4
|
|||
|
|||
|
Tasks don't obey predecessors if:
There are constraints There are actual dates against the tasks Can you post a copy of the file so I can look? or post a screen shot as an attachment? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| using a predecessor twice | ketanco | Project | 2 | 03-07-2014 04:52 PM |
Predecessor name displayed in a text field
|
Leah | Project | 7 | 02-07-2014 03:26 PM |
| Linking predecessor twice | ketanco | Project | 1 | 04-06-2012 08:49 AM |
| MS Project 2007 Predecessor Macro | dmpyne | Project | 1 | 12-14-2011 08:46 AM |
New to project - Predecessor Question
|
geissap | Project | 1 | 01-20-2011 10:00 AM |