#1
|
|||
|
|||
|
Check your fiscal year settings. File > Options, Schedule. Likely your fiscal year is set for something other than January. If you need fiscal years other than January, click the check box "Use starting year for FY numbering." |
|
#2
|
|||
|
|||
|
Thankyou very much JulieS, that was the problem.
Solved Cheers
|
|
|
|