Task split between two resources, but not equal effort
 
Join Date: Aug 2014
Posts: 14
pmgreen is on a distinguished road
Default Task split between two resources, but not equal effort

I have a task that is 16 hours and two resources are assigned.
Karen is doing 20% of the task, Raj is doing 80%. I thought this have Raj doing 12 hours of work and Karen 4 (round to whole #'s to make it easier).



However when I run a report, the task is still equally split.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Multiple resources on one task joday48 Project 2 08-01-2014 08:56 AM
Task split between two resources, but not equal effort How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Task split between two resources, but not equal effort several task must be completed out of hours, not split proj Project 1 01-13-2012 08:38 AM
Split a task fridos Project 2 05-30-2011 11:19 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft