I'm a little rusty. I'm working in 2010. I have been given the durations (in days) that tasks will take. I have multiple resources, all of whom will be working on the same tasks, all assigned units will differ, example, resource A will spend 60%, B will spend 20% and C will spend 20%. Apparently each resource with have a different number of effective hours per day. How should I handle this in the schedule? thanks JD |
|
![]() |
||||