#1
|
|||
|
|||
![]() Is there a way to check off a completed task from the gantt page without selecting the task and entering 100% complete? Thanks. |
#2
|
|||
|
|||
![]()
On the tracking toolbar is a 100% complete button. Select the tasks and click the button.
|
![]() |
|
![]() |
||||