![]() |
#1
|
|||
|
|||
![]()
Is there a way to check off a completed task from the gantt page without selecting the task and entering 100% complete? Thanks.
|
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Outlook 2010 Tasks - deleted when complete | theskymouse | Outlook | 0 | 01-10-2013 09:59 AM |
![]() |
Intruder | Project | 5 | 12-20-2012 08:35 AM |
Showing unscheduled tasks on Gantt chart | jaworski_m | Project | 0 | 11-20-2011 12:37 AM |
![]() |
Dawn1231a | Outlook | 1 | 08-02-2011 09:38 AM |
Stop the % Complete of subatasks from counting against the Main task | bzeyger | Project | 0 | 06-08-2010 06:19 AM |