JulieS JulieS is offline Duration days changing when updating % complete Windows 7 64bit Duration days changing when updating % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Project always assumes your original estimates (duration and work) were accurate. If you under report progress, it assume you still have the original amount of work to do. So, it may split the task, and reschedule the remaining work to occur as was planned. If you want to get more detailed than simply % complete, I suggest using the Tracking table to supply Actual Start, Actual and Remaining Duration, or Actual and Remaining Work.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
Duration days changing when updating % complete total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Duration days changing when updating % complete baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:38 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft