#1
|
|||
|
|||
|
Project always assumes your original estimates (duration and work) were accurate. If you under report progress, it assume you still have the original amount of work to do. So, it may split the task, and reschedule the remaining work to occur as was planned. If you want to get more detailed than simply % complete, I suggest using the Tracking table to supply Actual Start, Actual and Remaining Duration, or Actual and Remaining Work. |
|
#2
|
|||
|
|||
|
Slinkster - kindly do not post the same question to more than one forum - you are wasting the time of the volunteers who answer questions.
Also posted to: http://social.technet.microsoft.com/...=projectonline |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
| Change Resource Time vs. Duration when Updating Work column | lylel | Project | 3 | 07-23-2012 06:09 PM |
total slack not changing when changing duration
|
ketanco | Project | 1 | 02-11-2012 07:23 AM |
| updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
baseline duration of summary not updating. why
|
ketanco | Project | 1 | 12-14-2011 09:07 AM |