#1
|
|||
|
|||
![]()
Trying to create new schedule working 7 days a week, 12 hour days from 6am to 6pm. Have set up new calendar to reflect hrs per day 12, hrs per week 84, day p/month 28, Def Start Time 6:00AM, Def End Time 6:00PM.
When I enter duration as 1 day into the duration column, the gantt timeline shows as running from 6:00 AM to 6:00AM the following day (ie a 24 hour block), when it should only be a 21 hour block. I am running MS project 2013, however, need to save in 2003 format as numerous users accessing the file have differing versions of project. |
#2
|
|||
|
|||
![]()
If you show date/time in the Start and Finish fields, is the task scheduled correctly?
Just for clarity - you changed both the calendar (Change Working Time, Work Weeks tab) as well as the setting in File > Options, Schedule, yes? |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
showing calendar days by keeping normal workday calendar | ketanco | Project | 11 | 11-01-2013 08:27 AM |
![]() |
nmag | Outlook | 1 | 03-04-2013 04:52 AM |
Sync Outlook Calendar to Sharepoint site Calendar | kdogg121 | Outlook | 0 | 02-14-2013 08:50 AM |
Sync Outlook 2010 Calendar to Sharepoint Calendar | paankadu | Outlook | 0 | 12-08-2011 08:25 AM |
Make calendar events private in a shared calendar | Jackissimus | Outlook | 1 | 03-29-2011 04:48 PM |