Trying to create new schedule working 7 days a week, 12 hour days from 6am to 6pm. Have set up new calendar to reflect hrs per day 12, hrs per week 84, day p/month 28, Def Start Time 6:00AM, Def End Time 6:00PM.
When I enter duration as 1 day into the duration column, the gantt timeline shows as running from 6:00 AM to 6:00AM the following day (ie a 24 hour block), when it should only be a 21 hour block. I am running MS project 2013, however, need to save in 2003 format as numerous users accessing the file have differing versions of project.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
showing calendar days by keeping normal workday calendar ketanco Project 11 11-01-2013 08:27 AM
Calendar Sharing Calendar: How to set up a shared calendar with 2-3 users as owners nmag Outlook 1 03-04-2013 04:52 AM
Sync Outlook Calendar to Sharepoint site Calendar kdogg121 Outlook 0 02-14-2013 08:50 AM
Sync Outlook 2010 Calendar to Sharepoint Calendar paankadu Outlook 0 12-08-2011 08:25 AM
Make calendar events private in a shared calendar Jackissimus Outlook 1 03-29-2011 04:48 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft