Thread: [Solved] Calendar
View Single Post
 
Old 07-06-2014, 11:28 PM
CamRob15 CamRob15 is offline Windows XP Office 2013
Novice
 
Join Date: Jul 2014
Posts: 1
CamRob15 is on a distinguished road
Default Calendar

Trying to create new schedule working 7 days a week, 12 hour days from 6am to 6pm. Have set up new calendar to reflect hrs per day 12, hrs per week 84, day p/month 28, Def Start Time 6:00AM, Def End Time 6:00PM.
When I enter duration as 1 day into the duration column, the gantt timeline shows as running from 6:00 AM to 6:00AM the following day (ie a 24 hour block), when it should only be a 21 hour block. I am running MS project 2013, however, need to save in 2003 format as numerous users accessing the file have differing versions of project.
Reply With Quote