JulieS JulieS is offline Saturday off alternately Windows 7 64bit Saturday off alternately Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure I fully follow your question.

The default calendar in Project (Standard calendar) has all Saturdays as non-working. You can create a new calendar with every other Saturday as working and then copy that calendar to the Global template, making it available in all new projects.

So, is your question
  • How to create a calendar with every other Saturday as working time?
  • How to copy that calendar to Global?
  • Something else?
Please also let us know what version of Project. The directions for changing calendars may be different depending upon what version of Project you use.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Word 2013 macro to generate last day of each week (Saturday) CrabApple Word 1 11-08-2013 02:40 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft