A milestone by definition is a 0 duration activity- it is not an event in itself, but signifies that other tasks have been completed or that a point has been reached. Even the help within Project indicates this.
I cannot see how a 4 day activity should be marked as a milestone. If you need a milestone at this point, I would suggest inserting a new activity after the 4 day event (call it "xxx complete or whatever is significant), and link the 4 day activity to this, with the successors being transferred to the new milestone. If you look under format (on the main tabs), choos format/ bar styles, you will see that a milestone is shown as a diamond- a 0 duration task. A new item would establish the milestone, without affecting th eprogramme. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Enuhseh207 | Project | 1 | 02-23-2014 09:24 AM |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
![]() |
ketanco | Project | 5 | 12-15-2011 07:15 PM |
![]() |
caz46 | Project | 1 | 05-17-2011 07:51 AM |
Project 2010 - Milestone Font Colour | OTPM | Project | 1 | 05-11-2011 03:22 AM |