milestone with more than 0 day duration
in the milestone column i marked yes for an activity of 4 days duration (which happens to be a critical activity). and it became a milestone, still with 4 day duration but it is not shown as critical anymore , it is not in red at least. is it still critical? how does a milestone with a duration differ from a milestone of 0 duration? when we say milestone we understand by default 0 day correct?
|