#1
|
|||
|
|||
![]()
I am attaching a print screen of the project I am working on as I ran into a milestone wrapping back to left side of gantt chart when I think it's suppose to be at the end of a completed set of tasks on the right side where the finished tasks end? I am using MS Project 2007. See attachment. Thx
Last edited by Enuhseh207; 02-22-2014 at 07:17 PM. Reason: Forgot to id ms project version |
#2
|
|||
|
|||
![]()
The task is complete as indicated by the blue check mark. Once a task has been marked complete - it no longer follows predecessor data. Double click on the task and on the General tab - set the % complete to zero.
|
![]() |
|
![]() |
||||