critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

yes B is critical because of SS relation to G. and yes, critical activity is determined as you say. and here is also B finsih and Late finish date is same. because program thinks B's duration of 2 days as a fixed unchangeable thing.

but as you can see there is a 1 day gap between B end date and D start date. in other words, lets say B starts, and while performing B, something happens and B slows down and finish by 1 day delay. it will still be ok, no delay to the project will occur, although B is critical. Because B is only critical because of its start date, and NOT its finish date. and where is this information reflected? I assume nowhere?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
critical activity with floating end date floating month prompt schroca Word 2 05-12-2014 06:32 PM
critical activity with floating end date activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
critical activity with floating end date change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
critical activity with floating end date Floating object help ic-uc Drawing and Graphics 2 12-15-2008 09:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:01 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft