yes B is critical because of SS relation to G. and yes, critical activity is determined as you say. and here is also B finsih and Late finish date is same. because program thinks B's duration of 2 days as a fixed unchangeable thing.
but as you can see there is a 1 day gap between B end date and D start date. in other words, lets say B starts, and while performing B, something happens and B slows down and finish by 1 day delay. it will still be ok, no delay to the project will occur, although B is critical. Because B is only critical because of its start date, and NOT its finish date. and where is this information reflected? I assume nowhere? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
floating month prompt
|
schroca | Word | 2 | 05-12-2014 06:32 PM |
activity id number showing together with activity name
|
ketanco | Project | 1 | 04-08-2014 01:27 PM |
| tying to a critical activity | ketanco | Project | 1 | 08-04-2012 05:59 AM |
change color of critical activity texts
|
ketanco | Project | 3 | 01-05-2012 06:36 PM |
Floating object help
|
ic-uc | Drawing and Graphics | 2 | 12-15-2008 09:21 PM |