The reason task B is critical is due to the relationship (SS) with G. Float is determined by the forward pass (calculation of early start and early finish) and the backwards pass (late start and late finish). If there is no difference between a tasks Finish and Late Finish or Start and Late start, the task is critical.
Take a look at the Schedule table to see late start and late finish. The dates will match task B's start and finish. |
|
|