The reason task B is critical is due to the relationship (SS) with G. Float is determined by the forward pass (calculation of early start and early finish) and the backwards pass (late start and late finish). If there is no difference between a tasks Finish and Late Finish or Start and Late start, the task is critical.
Take a look at the Schedule table to see late start and late finish. The dates will match task B's start and finish.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
critical activity with floating end date floating month prompt schroca Word 2 05-12-2014 06:32 PM
critical activity with floating end date activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
critical activity with floating end date change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
critical activity with floating end date Floating object help ic-uc Drawing and Graphics 2 12-15-2008 09:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:13 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft