Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 03-07-2014, 07:12 AM
Guloluseus Guloluseus is offline using a predecessor twice Windows 7 64bit using a predecessor twice Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

If you have drywall as a predecessor to taping with an SS constraint, you cannnot have an FF predecessor as well- you would be to link start date to ther start AND finish of the predecessor.



I would suggest that if you know the amount of time between when drywall should be complete and tryingtaping should be complete, you use an FF+ predecessor. If you assume that taping should finish 1 day after walling finishes, the the predecessor for taping would be (drywall) FF+1d. This would link the two and ensure that taping i salways seen as finishing after the walling.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
using a predecessor twice Predecessor name displayed in a text field Leah Project 7 02-07-2014 03:26 PM
Linking predecessor twice ketanco Project 1 04-06-2012 08:49 AM
using a predecessor twice arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
MS Project 2007 Predecessor Macro dmpyne Project 1 12-14-2011 08:46 AM
using a predecessor twice New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft