Thanks Julie,
I believe this should be an option. Since earned value is already calculating the increased work, you should be able have Project recalculate the duration based on this. Chuck M. |
#2
|
|||
|
|||
![]()
If you wish Project to update actual and remaining duration and actual and remaining work, don't use Physical % complete. Use either % complete or % work complete.
|
![]() |
|
![]() |
||||