Physical % Complete and Task Duration
 
Join Date: Feb 2014
Posts: 2
ChuckM is on a distinguished road
Question Physical % Complete and Task Duration

I understand Physical % Complete with respect to Earned value. If I create a task with one resource that has work of 40 hours it will be scheduled for a week. If I enter completed work of 20 hours , and the Physical Progress is 25%, Earned Value will project the final cost for the resource based on 80 hours to complete the task. The % Complete will be 50% however.



What I don't see happening, is Project extending the task duration to two weeks, for the 80 hour work projection. Does Project do this, or do you have to manually increase the task work to 80 hours to get it to extend the duration?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Floating task duration dbsoccer Project 5 10-31-2013 09:10 AM
How to have multiple blocks of duration for one task AmezNez Project 3 10-10-2013 05:55 AM
Physical % Complete and Task Duration Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Physical % Complete and Task Duration complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:43 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft