JulieS JulieS is offline Help me about Project Pro 2010 ( How do can create Split Baseline?) Windows 7 64bit Help me about Project Pro 2010 ( How do can create Split Baseline?) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What do you mean by a split baseline? Baselines are a copy of task data when the baseline is saved - if the task was split - the baseline will be split.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to create statis Baseline date columns Ross Jackson Project 3 12-17-2015 04:00 PM
Project baseline duration Alka Project 1 11-20-2012 05:09 AM
Help me about Project Pro 2010 ( How do can create Split Baseline?) Push data automatically from Acess or Excel to create a Gantt chart in Project GST2212 Project 3 07-06-2012 12:52 PM
Help me about Project Pro 2010 ( How do can create Split Baseline?) Create a resource sheet in MS Project chabuk1 Project 8 05-01-2012 12:59 PM
[Office]How to create project timeline similar to this? Coderedpl Project 0 09-11-2009 01:23 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:34 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft