JulieS JulieS is offline Help me about Project Pro 2010 ( How do can create Split Baseline?) Windows 7 64bit Help me about Project Pro 2010 ( How do can create Split Baseline?) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I've looked at your project file and specifically at task 24 and I'm afraid I still don't know what you mean by split baseline.



Task 24 is baselined, although I am not sure why you have a summary task as well as the subtask. You do not have any resources assigned to the task and that is a usual way of splitting a task - edit the timescaled work in the Task Usage view and enter zeros in the work field. But, as you don't have assigned resources you can't do that.

Can you please explain in more detail what you need?
Reply With Quote
  #2  
Old 01-23-2014, 09:31 PM
huybuonvp huybuonvp is offline Help me about Project Pro 2010 ( How do can create Split Baseline?) Windows 8 Help me about Project Pro 2010 ( How do can create Split Baseline?) Office 2010 32bit
Novice
Help me about Project Pro 2010 ( How do can create Split Baseline?)
 
Join Date: Jan 2014
Posts: 5
huybuonvp is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
I've looked at your project file and specifically at task 24 and I'm afraid I still don't know what you mean by split baseline.

Task 24 is baselined, although I am not sure why you have a summary task as well as the subtask. You do not have any resources assigned to the task and that is a usual way of splitting a task - edit the timescaled work in the Task Usage view and enter zeros in the work field. But, as you don't have assigned resources you can't do that.

Can you please explain in more detail what you need?
Sorry. This is file download from internet to learn Project. I studying but can't create Baseline split task:
(If you open file by Project 2013 is not see Baseline Split. Only in Project 2010 is Ok.)
Thanks!
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to create statis Baseline date columns Ross Jackson Project 3 12-17-2015 04:00 PM
Project baseline duration Alka Project 1 11-20-2012 05:09 AM
Help me about Project Pro 2010 ( How do can create Split Baseline?) Push data automatically from Acess or Excel to create a Gantt chart in Project GST2212 Project 3 07-06-2012 12:52 PM
Help me about Project Pro 2010 ( How do can create Split Baseline?) Create a resource sheet in MS Project chabuk1 Project 8 05-01-2012 12:59 PM
[Office]How to create project timeline similar to this? Coderedpl Project 0 09-11-2009 01:23 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:46 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft