View Single Post
 
Old 01-22-2014, 09:31 PM
huybuonvp huybuonvp is offline Windows 8 Office 2010 32bit
Novice
 
Join Date: Jan 2014
Posts: 5
huybuonvp is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
What do you mean by a split baseline? Baselines are a copy of task data when the baseline is saved - if the task was split - the baseline will be split.
Firt, thanks JolieS anser. This's my file MPP: Learn MPP.zip
In this file MPP, i mark yellow at ID 24 ( Road Furniture)
I use Project 2010.
Thanks.
Reply With Quote