JulieS JulieS is offline Auto-level resources for parallel tasks with fixed work Windows 7 64bit Auto-level resources for parallel tasks with fixed work Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you need to restrict Task A to be worked on during specific times, consider creating a task calendar restricting work to only the morning hours. Assign that task calendar to Task A. Then resource leveling will do what you want it to. It will assign only 4 hours (at 100%) for Task B during the duration of Task A then 8 hours per day for the end of Task B.
Reply With Quote
 

Tags
level, resources



Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto-level resources for parallel tasks with fixed work Assigning Resources to Tasks rickw262 Project 1 01-18-2013 04:46 AM
Auto-level resources for parallel tasks with fixed work Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
Changing resources against tasks with actual values joday48 Project 3 06-28-2012 05:13 AM
Auto-level resources for parallel tasks with fixed work How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Constraining a fixed interval between two tasks Doug Sanderson Project 3 08-30-2011 09:01 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:05 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft