Yeah, awesome! I wasn't really aware of the calendar per task option.
Now I got the exact result that I tried to achieve.
I assigned a 4hrs calendar to Task A. When I assigned resources and used the resource leveling function, Task B was split at the end of Task A. First part assigned the resource 50%, the second part 100%.
See the result attached.
Thanks a lot!
|