Auto-level resources for parallel tasks with fixed work
Hi all,
I try to find a way to auto-level resources based on their available working hours per day.
There are two tasks starting at the same time (see Screenshot "problem"):
Task A takes 2 days
Task B takes 4 days
Both tasks start at the same time and have to be completed by the same resource. Work is fixed, so duration can vary.
I want the resource "User A" to work 50% for two days on both task. As soon as Task A is completed, User A should work a 100% on Task B.
Project either moves the task to resolve the problem or assigns the resource for 50% until the end of Task B (although 100% would be possible).
I want to achieve the result shown in screenshot "goal". Is there a way to do this without entering the values day by day in Resource Usage Sheet?
Thanks