![]() |
|
#1
|
|||
|
|||
|
Hi all,
I try to find a way to auto-level resources based on their available working hours per day. There are two tasks starting at the same time (see Screenshot "problem"): Task A takes 2 days Task B takes 4 days Both tasks start at the same time and have to be completed by the same resource. Work is fixed, so duration can vary. I want the resource "User A" to work 50% for two days on both task. As soon as Task A is completed, User A should work a 100% on Task B. Project either moves the task to resolve the problem or assigns the resource for 50% until the end of Task B (although 100% would be possible). I want to achieve the result shown in screenshot "goal". Is there a way to do this without entering the values day by day in Resource Usage Sheet? Thanks cineasta |
| Tags |
| level, resources |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Assigning Resources to Tasks
|
rickw262 | Project | 1 | 01-18-2013 04:46 AM |
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
|
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
| Changing resources against tasks with actual values | joday48 | Project | 3 | 06-28-2012 05:13 AM |
How to use fixed duration, fixed work and have resources/units leveled automatically?
|
Joeb | Project | 3 | 06-25-2012 04:18 PM |
| Constraining a fixed interval between two tasks | Doug Sanderson | Project | 3 | 08-30-2011 09:01 AM |