Old 11-20-2013, 02:21 AM
cineasta cineasta is offline Auto-level resources for parallel tasks with fixed work Windows 7 64bit Auto-level resources for parallel tasks with fixed work Office 2010 64bit
Novice
Auto-level resources for parallel tasks with fixed work
 
Join Date: Nov 2013
Posts: 3
cineasta is on a distinguished road
Default Thank you

Hi,

thanks a lot for your reply. I thought so...
In reality, two guys work on Task A 50% because the task can only be done by both of them together. They do this for two days in the morning. So the afternoon is free for the second task. After two days the entire day is available for the second task.

I will try a different approach in setting up my tasks. Maybe split the longer tasks in additional sub tasks.

Thanks for the feedback!
Reply With Quote
 

Tags
level, resources



Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto-level resources for parallel tasks with fixed work Assigning Resources to Tasks rickw262 Project 1 01-18-2013 04:46 AM
Auto-level resources for parallel tasks with fixed work Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
Changing resources against tasks with actual values joday48 Project 3 06-28-2012 05:13 AM
Auto-level resources for parallel tasks with fixed work How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Constraining a fixed interval between two tasks Doug Sanderson Project 3 08-30-2011 09:01 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:01 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft