JulieS JulieS is offline Auto-level resources for parallel tasks with fixed work Windows 7 64bit Auto-level resources for parallel tasks with fixed work Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No, sorry. The resource leveling command will never alter assignment units nor assign resources. Its only job is to move tasks so the resource's Peak Units are less than or equal to Max. Units.

Assign your resource at 100% to task A to get the 8 hours of work done in one day and then assign at 100% to task B to accomplish to 32 hours of work in 4 days. We are not as efficient at multi-tasking as we would like to think
Reply With Quote
 

Tags
level, resources



Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto-level resources for parallel tasks with fixed work Assigning Resources to Tasks rickw262 Project 1 01-18-2013 04:46 AM
Auto-level resources for parallel tasks with fixed work Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
Changing resources against tasks with actual values joday48 Project 3 06-28-2012 05:13 AM
Auto-level resources for parallel tasks with fixed work How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Constraining a fixed interval between two tasks Doug Sanderson Project 3 08-30-2011 09:01 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:19 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft