JulieS JulieS is offline MS Project not calculating earned value correctly Windows 7 64bit MS Project not calculating earned value correctly Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Is your status date set correctly to align with the end of the completed task? I see what you report only if I have a completed task (either ahead of schedule or before schedule) if the status date is before the completion date of the task.
For example: 5 day duration task one resource assigned at $1 per hour. 40 hours of work - $40 baseline cost. I mark the task 100% complete BUT my status date is Wednesday. My BCWP is only $24. I should not have progress through Friday if today is only Wednesday.
Another scenario: 5 day duration task 40 hours of work baseline cost = $40. It is Wednesday I have recorded 24 hours of Actual Work but I set the remaining work to zero. The task is complete - my status date is Wednesday and the BCWP is $40 even though the baseline finish for the task is not until Friday.


I hope this helps.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
earned value not calculating ketanco Project 3 08-16-2012 02:13 PM
MS Project not calculating earned value correctly Calculating earned value ketanco Project 3 08-13-2012 09:06 AM
MS Project not calculating earned value correctly summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM
MS Project not calculating earned value correctly How to apply budget for earned value analysis ttorneby Project 2 06-03-2010 04:52 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:42 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft