#2
|
|||
|
|||
|
Is your status date set correctly to align with the end of the completed task? I see what you report only if I have a completed task (either ahead of schedule or before schedule) if the status date is before the completion date of the task.
For example: 5 day duration task one resource assigned at $1 per hour. 40 hours of work - $40 baseline cost. I mark the task 100% complete BUT my status date is Wednesday. My BCWP is only $24. I should not have progress through Friday if today is only Wednesday. Another scenario: 5 day duration task 40 hours of work baseline cost = $40. It is Wednesday I have recorded 24 hours of Actual Work but I set the remaining work to zero. The task is complete - my status date is Wednesday and the BCWP is $40 even though the baseline finish for the task is not until Friday. I hope this helps. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Finding Earned Values for Different Baselines in a single project | pratik6312 | Project | 1 | 08-22-2013 11:18 AM |
| earned value not calculating | ketanco | Project | 3 | 08-16-2012 02:13 PM |
Calculating earned value
|
ketanco | Project | 3 | 08-13-2012 09:06 AM |
summary task calculating from project start
|
ketanco | Project | 1 | 01-02-2012 02:34 PM |
How to apply budget for earned value analysis
|
ttorneby | Project | 2 | 06-03-2010 04:52 PM |