I have tried copying by row, by cell, only some cells, etc. Each time is the same result.
I will update tomorrow with the update version. Thanks. |
#2
|
|||
|
|||
![]()
it is SP3
However, I tried again with the structure collapsed, and the dependencies shifted properly. thanks! |
#3
|
|||
|
|||
![]()
Great. The trick is to collapse the summary tasks and then copy the entire task - it should keep all of the relationships within the summary task correctly. Glad all is sorted.
|
![]() |
|
![]() |
||||