![]() |
#1
|
|||
|
|||
![]() Hi, I have the following scenario: I have a task with duration = 5 days (work = 40 hrs). When the task finish on day 3, I want the task following after it to start automatically and then also automatically adjust the rest of the schedule. I can do it manually by editing the duration/work to reflect 3 days/24 hrs, but I do not want to do this. Is there an easy way that this can be achieved? Thanks in advance... |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
providing early start date | ketanco | Project | 1 | 02-22-2013 02:32 PM |
Keep with Next/Keep Lines Together (to adjust page breaks) | lewiskm55 | Word | 1 | 05-02-2011 08:18 AM |
Pasting HTML into Excel (height auto-adjust) | c-tran | Excel | 0 | 03-11-2010 07:30 AM |
how do i adjust column to chosen width | hill0093 | Word | 0 | 09-19-2009 05:24 AM |
Adjust speed of ppt animation | gerryb | PowerPoint | 0 | 08-15-2009 08:45 AM |