There is no automatic way for Project to know that the task only took 3 days instead of 5 without you telling it. Display the Tracking table, set the Actual Finish to the finish date, the task will be marked 100% complete, the actual duration will show 3 days. Assuming the successor task is linked and does not have an actual start date, it will adjust accordingly.