Default Auto Adjust After Early Finish

Hi, I have the following scenario:

I have a task with duration = 5 days (work = 40 hrs). When the task finish on day 3, I want the task following after it to start automatically and then also automatically adjust the rest of the schedule. I can do it manually by editing the duration/work to reflect 3 days/24 hrs, but I do not want to do this. Is there an easy way that this can be achieved?

Thanks in advance...