![]() |
|
#1
|
|||
|
|||
|
Hi everyone
I'm currently building a project plan and trying to have some tasks at the very bottom that would show people's availability i.e. when they are on vacation. The problem is I can't see how to have more than one block of duration. So for example if they were on holiday for a week in December then 2 weeks in March. I would want the task duration to block out these periods so you could easily see it on the Gantt chart. Anyone know how I can do this? I imagine it must be possible as in project you could easily have tasks that stop and start throughout the duration i.e. gaps for other tasks to complete etc Thanks a lot! |
| Tags |
| duration, multiple, tasks |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Linking task duration to another task
|
branchi | Project | 1 | 08-15-2013 06:03 AM |
Question related to actual duration of task
|
Mac235 | Project | 1 | 08-14-2013 06:54 AM |
overtime work effecting task duration
|
user0044 | Project | 11 | 03-06-2012 07:20 AM |
| Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |
| Multiple task lists and multiple calendars | kballing | Outlook | 0 | 01-18-2011 10:23 AM |