Hi everyone
I'm currently building a project plan and trying to have some tasks at the very bottom that would show people's availability i.e. when they are on vacation. The problem is I can't see how to have more than one block of duration. So for example if they were on holiday for a week in December then 2 weeks in March. I would want the task duration to block out these periods so you could easily see it on the Gantt chart. Anyone know how I can do this? I imagine it must be possible as in project you could easily have tasks that stop and start throughout the duration i.e. gaps for other tasks to complete etc Thanks a lot! |
Tags |
duration, multiple, tasks |
|
![]() |
||||