View Single Post
 
Old 10-10-2013, 03:31 AM
AmezNez AmezNez is offline Windows 7 32bit Office 2010 32bit
Novice
 
Join Date: Oct 2013
Posts: 4
AmezNez is on a distinguished road
Default How to have multiple blocks of duration for one task

Hi everyone

I'm currently building a project plan and trying to have some tasks at the very bottom that would show people's availability i.e. when they are on vacation.

The problem is I can't see how to have more than one block of duration. So for example if they were on holiday for a week in December then 2 weeks in March. I would want the task duration to block out these periods so you could easily see it on the Gantt chart.

Anyone know how I can do this?

I imagine it must be possible as in project you could easily have tasks that stop and start throughout the duration i.e. gaps for other tasks to complete etc

Thanks a lot!
Reply With Quote