JulieS JulieS is offline Replicating tasks in a single project Windows 7 64bit Replicating tasks in a single project Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Are you selecting the task by the row number and then copying? Have you tried collapsing the summary task, copying the summary and pasting? What service pack do you have applied to Project 2003? I believe it is up to SP-3
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project tasks moving automatically tcalderini Project 3 09-06-2013 12:25 PM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
Replicating tasks in a single project How to help - Project 2007 - Scheduling tasks during specific windows of opportunity apexian Project 1 07-12-2013 05:16 AM
Calender icons replicating AmyBrink Outlook 0 04-16-2013 01:04 PM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft