Default Critical Task - Microsoft Project 2010

Can anyone explain me, when we see in network diagram of any project (which does not have any link between the tasks), the first task is being shown as "Critical Task" (with RED border)?

Thanks



Mac
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Task - Microsoft Project 2010 How to show critical task bars in different color? ketanco Project 1 05-17-2012 05:17 AM
Critical Task - Microsoft Project 2010 Microsoft Project 2010 SYNC Problem paul14louie Project 3 04-13-2012 11:36 AM
Microsoft Project 2010 automation without VS Fil Project 0 09-15-2011 10:17 AM
MS Project 2010 Synch to task list rinalgi1 Project 1 09-14-2011 12:37 AM
Critical Task - Microsoft Project 2010 Microsoft Project 2010 taking up to 10mins to open file from network share. BITS Project 1 06-01-2011 09:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:16 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft