Originally Posted by JulieS View Post
None of your tasks are linked, therefore the task with the longest duration (initially Task a) is the task on the critical path - it is the task that is driving the latest date in the project. When you increase tasks b & C to 3 days duration they now all finish last and are all critical. Changing the start date of A to June 5 with 3 days duration still makes it finish last.

So, what are you expecting?
Julie,

Thanks for your reply. The task with the longest duration is a "critical" task.