Hi Everybody,
my issue : when I update the %Complete with 100% of task entry through SharePoint after the Synchronisation the same task in MS Project 2010 becomes 99%... Someone has an idea why 100% becomes 99% ? |
#2
|
|||
|
|||
![]()
Hi
I have had the same issue recently. It appears to be an issue with Project 2010. What you need to do is update the summary task %Complete to 100% manually. Not ideal I know but as long as all the child tasks are 100% complete then you are safe to mark the summary task as 100% complete manually. Tony(OTPM) |
![]() |
|
![]() |
||||