![]() Ah, but "two days of effort" is two days of work - not duration. You are entering duration and Project will calculate work - that is what it is programmed to do. |
#2
|
|||
|
|||
![]()
Hi Julie
Thanks for your response. ![]() ![]() ![]() ![]() ![]() I have been using Project for many years believe it or not but even I forget the basics sometimes. This is why this forum is so invaluable. Thanks again. Tony |
#3
|
|||
|
|||
![]()
You're welcome Tony and thanks for the feedback.
|
![]() |
|
![]() |
||||