Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 10-03-2012, 09:34 AM
jsteczak jsteczak is offline I am unsure I assigned a task out to a resource. Windows 7 32bit I am unsure I assigned a task out to a resource. Office 2010 32bit
Novice
I am unsure I assigned a task out to a resource.
 
Join Date: Oct 2012
Posts: 2
jsteczak is on a distinguished road
Default I am unsure I assigned a task out to a resource.

I am using Project 2003 and last week I assigned a task to a resource. This week I was told I never assigned the task. How can I track whether or not the task was assigned last week? Can I highlight the task and then select some option to review history of activity?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
I am unsure I assigned a task out to a resource. MS Project Crash after resource sheet assigned Imagios Project 7 04-30-2012 06:58 AM
Reporting ManDays on people not fully assigned to the Project Imagios Project 9 10-10-2011 04:36 AM
Task Form disappearing when assigned zoids Outlook 0 03-27-2011 05:01 PM
Hyperlink assigned sounds do not play Starscream PowerPoint 0 03-08-2011 02:14 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft