Old 12-24-2011, 05:55 PM
ketanco ketanco is offline moving one task from one row to another Windows 7 64bit moving one task from one row to another Office 2007
Expert
moving one task from one row to another
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

i havent tried with 2007 yet but when i tried this in ms project 2010, say there are tasks A B C. B is successor of A. when I moved B under C, it didnt at first update sucessor of task A to show the new row of B. then i undo and redo and this time it did. why did this happen any ideas?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
moving one task from one row to another arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
moving one task from one row to another Moving Outlook to new PC TheProdigalScribe Outlook 1 10-25-2011 06:37 PM
moving one task from one row to another Moving columns plantzj Word 3 09-17-2011 10:30 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
moving one task from one row to another Moving formula range multiple cells when moving sum over one cell FraserKitchell Excel 4 02-26-2010 10:38 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:10 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft