#3
|
|||
|
|||
|
i havent tried with 2007 yet but when i tried this in ms project 2010, say there are tasks A B C. B is successor of A. when I moved B under C, it didnt at first update sucessor of task A to show the new row of B. then i undo and redo and this time it did. why did this happen any ideas?
|
|
|