Hi,
I have an issue. When I add a contour, MS Project increases my duration by 1.6 days, therefore the end date moves as well.


The reason it does that is if the resource, in the flat contour, works 4hr/day, the backloaded contour basically will start out low, and go no higher than 4hr/day towards the end. Therefore duration has to increase. I don't want that. What I want is to start each resource low, but than towards the end go above 4 hrs to make up for lost time before and keep the duration the same and the end date the same. Can this be done?

Thanks
Reply With Quote
 

Thread Tools
Display Modes


Other Forums: Access Forums

All times are GMT -7. The time now is 11:08 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft