Hi,
I have an issue. When I add a contour, MS Project increases my duration by 1.6 days, therefore the end date moves as well.
The reason it does that is if the resource, in the flat contour, works 4hr/day, the backloaded contour basically will start out low, and go no higher than 4hr/day towards the end. Therefore duration has to increase. I don't want that. What I want is to start each resource low, but than towards the end go above 4 hrs to make up for lost time before and keep the duration the same and the end date the same. Can this be done?

Thanks