Hi,
I have an issue. When I add a contour, MS Project increases my duration by 1.6 days, therefore the end date moves as well.


The reason it does that is if the resource, in the flat contour, works 4hr/day, the backloaded contour basically will start out low, and go no higher than 4hr/day towards the end. Therefore duration has to increase. I don't want that. What I want is to start each resource low, but than towards the end go above 4 hrs to make up for lost time before and keep the duration the same and the end date the same. Can this be done?

Thanks
Reply With Quote
 



Other Forums: Access Forums

All times are GMT -7. The time now is 08:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft